Waste water treatment plant AT 200 oval and AT 225 oval.
Sewage treatment plants ensure the cleaning of sewage waste water produced by the employees of the extensive Mercado Libre warehouse.
Wastewater is discharged separately from two sources and then flows by gravity into the pumping station or equalization tank, from where they are pushed by a sludge pump into the biological reactors of the WWTP.
Cleaned waters are discharged into the recipient.
Capacity and technological parameters:
Technical parameters of AT 225 oval sewage treatment plant
Reactor length: 12000 mm
Reactor height: 2500 mm
Reactor width: 2260 mm
Daily flow: 33.80 m³/d
Load: 13.5 kg BOD5 /d
Technical parameters of AT 200 oval WWTP
Reactor length: 10960 mm
Reactor height: 2500 mm
Reactor width: 2260 mm
Daily flow: 30.00 m³/d
Load: 12.0 kg BOD /d